Question

A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?

Options

  • AUpdate the project plan to accommodate the changes.
  • BPerform an impact analysis.
  • COrganize a stakeholder meeting to review the changes.
  • DChange the project scope to reflect the change request.