CompTIA
JK0-017 · Question #473
A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?
The correct answer is B. Perform an impact analysis. See the full explanation below for the reasoning.
Question
A project manager is presented with a change request for an ongoing project. Which of the following would be the FIRST action?
Options
- AUpdate the project plan to accommodate the changes.
- BPerform an impact analysis.
- COrganize a stakeholder meeting to review the changes.
- DChange the project scope to reflect the change request.
How the community answered
(19 responses)- A11% (2)
- B79% (15)
- C5% (1)
- D5% (1)
Community Discussion
No community discussion yet for this question.