In pre-project setup, which of the following must be completed prior to validating a project?

The correct answer is A. Project definition. See the full explanation below for the reasoning.

Question

In pre-project setup, which of the following must be completed prior to validating a project?

Options

  • AProject definition
  • BPreliminary SOW
  • CProject charter
  • DStakeholder approval

How the community answered

(30 responses)
  • A
    83% (25)
  • B
    3% (1)
  • C
    3% (1)
  • D
    10% (3)