In pre-project setup, which of the following must be completed prior to validating a project?
The correct answer is A. Project definition. See the full explanation below for the reasoning.
Question
In pre-project setup, which of the following must be completed prior to validating a project?
Options
- AProject definition
- BPreliminary SOW
- CProject charter
- DStakeholder approval
How the community answered
(30 responses)- A83% (25)
- B3% (1)
- C3% (1)
- D10% (3)