JK0-017 · Question #458
A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?
The correct answer is A. The costs are currently over the estimates. See the full explanation below for the reasoning.
Question
A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?
Options
- AThe costs are currently over the estimates.
- BThe costs and the estimates are about the same.
- CThe costs are currently under the estimates.
- DThe earned value is greater than the actual cost.
How the community answered
(57 responses)- A72% (41)
- B9% (5)
- C14% (8)
- D5% (3)