JK0-017 · Question #458

A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?

The correct answer is A. The costs are currently over the estimates. See the full explanation below for the reasoning.

Question

A project has a CPI of 0.6. Which of the following would BEST describe the cost-efficiency of the project?

Options

  • AThe costs are currently over the estimates.
  • BThe costs and the estimates are about the same.
  • CThe costs are currently under the estimates.
  • DThe earned value is greater than the actual cost.

How the community answered

(57 responses)
  • A
    72% (41)
  • B
    9% (5)
  • C
    14% (8)
  • D
    5% (3)