The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:

The correct answer is B. bottom-up estimating. See the full explanation below for the reasoning.

Question

The method of cost-estimating whereby the costs of the individual work packages are aggregated to form the full cost-estimate is called:

Options

  • Aparametric estimating.
  • Bbottom-up estimating.
  • Cexpert judgment.
  • Danalogous estimating.

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    76% (35)
  • C
    15% (7)
  • D
    7% (3)