CompTIA
JK0-017 · Question #44
A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?
The correct answer is A. Assign the request a tracking number and record in change request log. See the full explanation below for the reasoning.
Question
A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?
Options
- AAssign the request a tracking number and record in change request log
- BRecruit new project team members to expedite the change's completion date
- CPerform an analysis on the requested change submitted by the stakeholder
- DSubmit stakeholder's change request to the change control board
How the community answered
(42 responses)- A71% (30)
- B10% (4)
- C17% (7)
- D2% (1)
Community Discussion
No community discussion yet for this question.