A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?

The correct answer is A. Assign the request a tracking number and record in change request log. See the full explanation below for the reasoning.

Question

A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?

Options

  • AAssign the request a tracking number and record in change request log
  • BRecruit new project team members to expedite the change's completion date
  • CPerform an analysis on the requested change submitted by the stakeholder
  • DSubmit stakeholder's change request to the change control board

How the community answered

(42 responses)
  • A
    71% (30)
  • B
    10% (4)
  • C
    17% (7)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.