Which of the following describes the work package level of a WBS?
The correct answer is C. The lowest level. See the full explanation below for the reasoning.
Question
Which of the following describes the work package level of a WBS?
Options
- AProject phases
- BMajor deliverables
- CThe lowest level
- DThe project name
How the community answered
(32 responses)- A9% (3)
- B16% (5)
- C72% (23)
- D3% (1)