Which of the following describes the work package level of a WBS?

The correct answer is C. The lowest level. See the full explanation below for the reasoning.

Question

Which of the following describes the work package level of a WBS?

Options

  • AProject phases
  • BMajor deliverables
  • CThe lowest level
  • DThe project name

How the community answered

(32 responses)
  • A
    9% (3)
  • B
    16% (5)
  • C
    72% (23)
  • D
    3% (1)