nerdexam
CompTIA

JK0-017 · Question #430

Which of the following documents would a project manager review to determine all the identified risks on a project?

The correct answer is B. Risk register. See the full explanation below for the reasoning.

Question

Which of the following documents would a project manager review to determine all the identified risks on a project?

Options

  • ARisk matrix
  • BRisk register
  • CRisk response
  • DRisk baseline

How the community answered

(50 responses)
  • A
    6% (3)
  • B
    78% (39)
  • C
    12% (6)
  • D
    4% (2)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice