Which of the following documents would a project manager review to determine all the identified risks on a project?
The correct answer is B. Risk register. See the full explanation below for the reasoning.
Question
Which of the following documents would a project manager review to determine all the identified risks on a project?
Options
- ARisk matrix
- BRisk register
- CRisk response
- DRisk baseline
How the community answered
(50 responses)- A6% (3)
- B78% (39)
- C12% (6)
- D4% (2)