nerdexam
CompTIA

JK0-017 · Question #429

A project manager is completing a project schedule network diagram using dummy activities to show all logical relationships. Which of the following tools is the project manager using?

The correct answer is A. ADM. See the full explanation below for the reasoning.

Question

A project manager is completing a project schedule network diagram using dummy activities to show all logical relationships. Which of the following tools is the project manager using?

Options

  • AADM
  • BWBS
  • CAON
  • DPDM

How the community answered

(32 responses)
  • A
    84% (27)
  • B
    3% (1)
  • C
    9% (3)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice