The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped. Which of the following should the project manager do?
The correct answer is D. Schedule a meeting with the stakeholders to review the impact. See the full explanation below for the reasoning.
Question
The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped. Which of the following should the project manager do?
Options
- AProceed with the release and document the adjustment in the change log.
- BProceed with the release and tell the SME the component will be added in a special release.
- CDelay the release until the component is tested.
- DSchedule a meeting with the stakeholders to review the impact.
How the community answered
(52 responses)- A4% (2)
- B15% (8)
- C8% (4)
- D73% (38)