The project team has completed phase testing. After testing, a subject matter expert (SME) notices that a component was skipped. Which of the following should the project manager do?

Options

  • AProceed with the release and document the adjustment in the change log.
  • BProceed with the release and tell the SME the component will be added in a special release.
  • CDelay the release until the component is tested.
  • DSchedule a meeting with the stakeholders to review the impact.