An adjustment to the project has been approved and funding granted, but the project manager feels the modification is out of scope. Which of the following should the project manager do?

The correct answer is D. Make the adjustment but document the concern. See the full explanation below for the reasoning.

Question

An adjustment to the project has been approved and funding granted, but the project manager feels the modification is out of scope. Which of the following should the project manager do?

Options

  • ASchedule a meeting with the project sponsor to reject the adjustment.
  • BRefuse to make the adjustment and send a recommendation to the review board.
  • CMake the adjustment and wait for another review.
  • DMake the adjustment but document the concern.

How the community answered

(50 responses)
  • A
    8% (4)
  • B
    4% (2)
  • C
    12% (6)
  • D
    76% (38)