Which of the following shows a project that is presently over its financial budget?

The correct answer is D. CPI = 0.8. See the full explanation below for the reasoning.

Question

Which of the following shows a project that is presently over its financial budget?

Options

  • ACPI = 1.4
  • BCPI = 0
  • CCV = +$11,000
  • DCPI = 0.8

How the community answered

(43 responses)
  • A
    7% (3)
  • B
    12% (5)
  • C
    2% (1)
  • D
    79% (34)