nerdexam
CompTIA

JK0-017 · Question #413

An important team member will not be available to complete a project. The project manager selects a new team member and trains the new team member on the project tasks. The project manager is using…

The correct answer is B. Mitigation of the risk. See the full explanation below for the reasoning.

Question

An important team member will not be available to complete a project. The project manager selects a new team member and trains the new team member on the project tasks. The project manager is using which of the following risk response techniques to resolve the issue?

Options

  • AMonitor the risk
  • BMitigation of the risk
  • CAcceptance of the risk
  • DTransference of the risk

How the community answered

(36 responses)
  • A
    8% (3)
  • B
    75% (27)
  • C
    14% (5)
  • D
    3% (1)

Community Discussion