Which of the following cost estimating techniques uses previous, similar projects as a basis of estimating costs for the current project?

The correct answer is D. Analogous estimating. See the full explanation below for the reasoning.

Question

Which of the following cost estimating techniques uses previous, similar projects as a basis of estimating costs for the current project?

Options

  • ATop-down estimating
  • BParametric estimating
  • CBottom-up estimating
  • DAnalogous estimating

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    16% (7)
  • C
    5% (2)
  • D
    73% (32)