Which of the following would be a direct output of the initiating process group? (Select Two).
The correct answer is A. Project charter E. Preliminary scope statement. See the full explanation below for the reasoning.
Question
Which of the following would be a direct output of the initiating process group? (Select Two).
Options
- AProject charter
- BProject management plan
- CStatement of Work (SOW)
- DWork Breakdown Structure (WBS)
- EPreliminary scope statement
How the community answered
(35 responses)- A86% (30)
- B3% (1)
- C3% (1)
- D9% (3)