The project manager has noticed that meeting attendance rates are declining. Regular attendees prefer to talk about the past or upcoming weekend as opposed to reporting on project updates. Which of…

The correct answer is D. Establish ground rules, distribute an agenda, and use a facilitator. See the full explanation below for the reasoning.

Question

The project manager has noticed that meeting attendance rates are declining. Regular attendees prefer to talk about the past or upcoming weekend as opposed to reporting on project updates. Which of the following shows how the project manager should respond?

Options

  • ATake no action. Team bonding is important. Those that cannot attend are probably attending
  • BChange the meeting format to be a daily stand-up of no longer than 15 minutes.
  • CEscalate non attendance to functional line managers. Cut off non-related discussions.
  • DEstablish ground rules, distribute an agenda, and use a facilitator.

How the community answered

(44 responses)
  • A
    7% (3)
  • B
    11% (5)
  • C
    5% (2)
  • D
    77% (34)