During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?
Options
- ABottom-up estimating
- BRolling wave planning
- CResource leveling
- DFast tracking