During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project…

The correct answer is D. Fast tracking. See the full explanation below for the reasoning.

Question

During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques will the project manager MOST likely use to deliver the project on time?

Options

  • ABottom-up estimating
  • BRolling wave planning
  • CResource leveling
  • DFast tracking

How the community answered

(56 responses)
  • A
    11% (6)
  • B
    7% (4)
  • C
    2% (1)
  • D
    80% (45)