JK0-017 · Question #368

The project is running behind schedule because one of the developers has taken an unscheduled vacation. The project manager informs the developer that any further unauthorized absence will result in…

The correct answer is D. Confronting. See the full explanation below for the reasoning.

Question

The project is running behind schedule because one of the developers has taken an unscheduled vacation. The project manager informs the developer that any further unauthorized absence will result in removal from the project. Which of the following resolution techniques was used?

Options

  • AForcing
  • BNegotiating
  • CAvoiding
  • DConfronting

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    7% (3)
  • C
    15% (7)
  • D
    76% (35)