CompTIA
JK0-017 · Question #362
Schedule dependenciesinclude:(Select TWO).
The correct answer is A. Successor activities D. Predecessor activities. See the full explanation below for the reasoning.
Question
Schedule dependenciesinclude:(Select TWO).
Options
- ASuccessor activities
- BRisks
- CConstraints
- DPredecessor activities
- EIssues
- FAssumptions
How the community answered
(49 responses)- A71% (35)
- B6% (3)
- C2% (1)
- E4% (2)
- F16% (8)
Community Discussion
No community discussion yet for this question.