Schedule dependenciesinclude:(Select TWO).

The correct answer is A. Successor activities D. Predecessor activities. See the full explanation below for the reasoning.

Question

Schedule dependenciesinclude:(Select TWO).

Options

  • ASuccessor activities
  • BRisks
  • CConstraints
  • DPredecessor activities
  • EIssues
  • FAssumptions

How the community answered

(49 responses)
  • A
    71% (35)
  • B
    6% (3)
  • C
    2% (1)
  • E
    4% (2)
  • F
    16% (8)