The formula for Schedule Performance Index (SPI) is:

The correct answer is B. SPI = EV/PV. See the full explanation below for the reasoning.

Question

The formula for Schedule Performance Index (SPI) is:

Options

  • ASPI = SV/PV
  • BSPI = EV/PV
  • CSPI = EV/SV
  • DSPI = PV/EV

How the community answered

(48 responses)
  • A
    6% (3)
  • B
    73% (35)
  • C
    17% (8)
  • D
    4% (2)