The formula for Schedule Performance Index (SPI) is:
The correct answer is B. SPI = EV/PV. See the full explanation below for the reasoning.
Question
The formula for Schedule Performance Index (SPI) is:
Options
- ASPI = SV/PV
- BSPI = EV/PV
- CSPI = EV/SV
- DSPI = PV/EV
How the community answered
(48 responses)- A6% (3)
- B73% (35)
- C17% (8)
- D4% (2)