While working on a project, a workaround is implemented to deal with an unforeseen event. Which of the following should be the NEXT step?

The correct answer is D. Assess the action taken to determine additional impacts to the project. See the full explanation below for the reasoning.

Question

While working on a project, a workaround is implemented to deal with an unforeseen event. Which of the following should be the NEXT step?

Options

  • AContinue with the project as planned
  • BUpdate the risk register
  • CUpdate the project management plan with information about the workaround
  • DAssess the action taken to determine additional impacts to the project

How the community answered

(67 responses)
  • A
    13% (9)
  • B
    3% (2)
  • C
    7% (5)
  • D
    76% (51)