While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?
The correct answer is B. Issue log. See the full explanation below for the reasoning.
Question
While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?
Options
- AStakeholder register
- BIssue log
- CRisk register
- DChange log