CompTIA
JK0-017 · Question #321
Which of the following MUST be clearly defined in a project charter?
The correct answer is B. Scope. See the full explanation below for the reasoning.
Question
Which of the following MUST be clearly defined in a project charter?
Options
- AQuality
- BScope
- CAction items
- DWBS
How the community answered
(36 responses)- A3% (1)
- B78% (28)
- C14% (5)
- D6% (2)
Community Discussion
No community discussion yet for this question.