The project manager has received an approved change request. Which of the following actions should the project manager take NEXT?
The correct answer is D. Develop a plan to incorporate the change into the project. See the full explanation below for the reasoning.
Question
The project manager has received an approved change request. Which of the following actions should the project manager take NEXT?
Options
- ASchedule a meeting with the change advisory board to discuss the impact of the change
- BPerform a probability and impact assessment on the approved change
- CHold a team meeting to ensure the change is immediately implemented
- DDevelop a plan to incorporate the change into the project
How the community answered
(27 responses)- A4% (1)
- B7% (2)
- C15% (4)
- D74% (20)