Which of the following techniques can a project manager use to assist with quality planning? (Select THREE).

The correct answer is A. Peer review C. Inspection F. Benchmarking. See the full explanation below for the reasoning.

Question

Which of the following techniques can a project manager use to assist with quality planning? (Select THREE).

Options

  • APeer review
  • BCritical Chain Method (CCM)
  • CInspection
  • DPerformance Evaluation and Review Technique (PERT)
  • EWork Breakdown Structure (WBS)
  • FBenchmarking

How the community answered

(55 responses)
  • A
    82% (45)
  • B
    2% (1)
  • D
    9% (5)
  • E
    7% (4)