In which of the following areas would a transition plan be used?

Options

  • AAs a project phase is completed and the project shifts to a new phase
  • BAt the end of the project to transfer maintenance responsibilities
  • CAfter the project receives approval and becomes an active project
  • DWhen the project manager is added to the project and the project authority shifts to their