JK0-017 · Question #270
In which of the following areas would a transition plan be used?
The correct answer is B. At the end of the project to transfer maintenance responsibilities. See the full explanation below for the reasoning.
Question
In which of the following areas would a transition plan be used?
Options
- AAs a project phase is completed and the project shifts to a new phase
- BAt the end of the project to transfer maintenance responsibilities
- CAfter the project receives approval and becomes an active project
- DWhen the project manager is added to the project and the project authority shifts to their
How the community answered
(26 responses)- A8% (2)
- B85% (22)
- C4% (1)
- D4% (1)