An organization's quality control team has informed the project manager that a project deliverable is not within specifications. Which of the following tools would be the MOST useful to determine…

The correct answer is C. Pareto Chart. See the full explanation below for the reasoning.

Question

An organization's quality control team has informed the project manager that a project deliverable is not within specifications. Which of the following tools would be the MOST useful to determine the most common issues?

Options

  • AKey Performance Indicators
  • BScatter Diagram
  • CPareto Chart
  • DSWOT Analysis

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    76% (16)
  • D
    14% (3)