A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?

Options

  • AChange control form
  • BRisk register
  • CWork Breakdown Structure (WBS)
  • DIssues log