nerdexam
CompTIA

JK0-017 · Question #25

A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager…

The correct answer is D. Issues log. See the full explanation below for the reasoning.

Question

A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The project manager should update which of the following?

Options

  • AChange control form
  • BRisk register
  • CWork Breakdown Structure (WBS)
  • DIssues log

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    5% (2)
  • C
    12% (5)
  • D
    81% (35)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice