There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third project team is behind…
The correct answer is B. Meet with the teams to clarify the schedule and the quality standards expected. See the full explanation below for the reasoning.
Question
There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third project team is behind schedule, but their product meets the quality standards. Which of the following should be the NEXT step for the project manager?
Options
- AInform the stakeholders that the project is behind schedule.
- BMeet with the teams to clarify the schedule and the quality standards expected.
- CCrash the schedule to meet the project timeline.
- DFast track the schedule to complete the project on time without impacting the quality of the product.
How the community answered
(63 responses)- A3% (2)
- B81% (51)
- C11% (7)
- D5% (3)