CompTIA
JK0-017 · Question #244
The stakeholder has notified the project manager that new priorities have caused them to shift all of the business subject matter expert resources to a new project for one year. The BEST course of…
The correct answer is B. Project cancellation. See the full explanation below for the reasoning.
Question
The stakeholder has notified the project manager that new priorities have caused them to shift all of the business subject matter expert resources to a new project for one year. The BEST course of action for the project manager is:
Options
- APhase gate review.
- BProject cancellation.
- CProject completion.
- DStage completion.
How the community answered
(50 responses)- A16% (8)
- B72% (36)
- C8% (4)
- D4% (2)
Community Discussion
No community discussion yet for this question.