The BEST time to communicate stakeholder expectations to the project team is:

The correct answer is B. During the project kick-off meeting. See the full explanation below for the reasoning.

Question

The BEST time to communicate stakeholder expectations to the project team is:

Options

  • ADuring bi-weekly status meetings.
  • BDuring the project kick-off meeting.
  • CDuring the development of the work breakdown structure.
  • DAt regular intervals as defined in the communications management plan.