nerdexam
CompTIA

JK0-017 · Question #240

In month nine of a 12 month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the customer a more…

The correct answer is D. CV = EV - AC. See the full explanation below for the reasoning.

Question

In month nine of a 12 month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the customer a more accurate assessment, the project manager calculates the Cost Variance (CV) using which of the following formulas?

Options

  • ACV = PV - AC
  • BCV = AC - EV
  • CCV = EV - PV
  • DCV = EV - AC

How the community answered

(57 responses)
  • A
    12% (7)
  • B
    5% (3)
  • C
    2% (1)
  • D
    81% (46)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice