CompTIA
JK0-017 · Question #240
In month nine of a 12 month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the customer a more…
The correct answer is D. CV = EV - AC. See the full explanation below for the reasoning.
Question
In month nine of a 12 month project, the customer approaches the project manager believing the project is at risk because 85% of the funds have been expended already. To give the customer a more accurate assessment, the project manager calculates the Cost Variance (CV) using which of the following formulas?
Options
- ACV = PV - AC
- BCV = AC - EV
- CCV = EV - PV
- DCV = EV - AC
How the community answered
(57 responses)- A12% (7)
- B5% (3)
- C2% (1)
- D81% (46)
Community Discussion
No community discussion yet for this question.