In order to ensure higher commitment levels, estimates should be created, or approved by:
The correct answer is A. The person doing the work. See the full explanation below for the reasoning.
Question
In order to ensure higher commitment levels, estimates should be created, or approved by:
Options
- AThe person doing the work
- BThe customer
- CThe project manager
- DKey stakeholders
How the community answered
(44 responses)- A70% (31)
- B5% (2)
- C7% (3)
- D18% (8)