CompTIA
JK0-017 · Question #216
Which of the following is a zero time activity?
The correct answer is A. Milestone. See the full explanation below for the reasoning.
Question
Which of the following is a zero time activity?
Options
- AMilestone
- BCritical path
- CDeliverable
- DWork package
How the community answered
(25 responses)- A84% (21)
- B4% (1)
- C8% (2)
- D4% (1)
Community Discussion