In QC testing, the project manager determines that the deliverable is outside of the specification limits. Which of the following processes allowed the project manager to make this determination?

The correct answer is D. Identify variance. See the full explanation below for the reasoning.

Question

In QC testing, the project manager determines that the deliverable is outside of the specification limits. Which of the following processes allowed the project manager to make this determination?

Options

  • AReview change log
  • BRegression analysis
  • CMonitoring work performance
  • DIdentify variance

How the community answered

(30 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    17% (5)
  • D
    70% (21)