A project team is meeting monthly for their project risk review. During the brainstorm, one of the team members mentions that a risk to the project could be a delay with the servers. Which of the…

The correct answer is C. Avoid. See the full explanation below for the reasoning.

Question

A project team is meeting monthly for their project risk review. During the brainstorm, one of the team members mentions that a risk to the project could be a delay with the servers. Which of the following is the BEST response?

Options

  • AExploit
  • BEnhance
  • CAvoid
  • DShare

How the community answered

(27 responses)
  • A
    4% (1)
  • B
    11% (3)
  • C
    81% (22)
  • D
    4% (1)