CompTIA
JK0-017 · Question #177
A project team is meeting monthly for their project risk review. During the brainstorm, one of the team members mentions that a risk to the project could be a delay with the servers. Which of the…
The correct answer is C. Avoid. See the full explanation below for the reasoning.
Question
A project team is meeting monthly for their project risk review. During the brainstorm, one of the team members mentions that a risk to the project could be a delay with the servers. Which of the following is the BEST response?
Options
- AExploit
- BEnhance
- CAvoid
- DShare
How the community answered
(27 responses)- A4% (1)
- B11% (3)
- C81% (22)
- D4% (1)
Community Discussion