JK0-017 · Question #176

A project team is about to deliver on a two year long project when they are informed of new Government laws that directly affect the product. The team meets with their stakeholders to discuss the…

The correct answer is B. Create a change request. See the full explanation below for the reasoning.

Question

A project team is about to deliver on a two year long project when they are informed of new Government laws that directly affect the product. The team meets with their stakeholders to discuss the impact to the project and determine that additional laws need to be taken into account before go-live. The NEXT step the project manager needs to take is:

Options

  • ARe-direct the development team.
  • BCreate a change request.
  • CUpdate the issues log.
  • DHold a meeting with the users.

How the community answered

(65 responses)
  • A
    3% (2)
  • B
    71% (46)
  • C
    9% (6)
  • D
    17% (11)