CompTIA
JK0-017 · Question #174
After a project team has almost completed the development on the project's original requirements, the users identify functionality that is necessary but was not in the original requirements. The…
The correct answer is D. Generate a change request. See the full explanation below for the reasoning.
Question
After a project team has almost completed the development on the project's original requirements, the users identify functionality that is necessary but was not in the original requirements. The project manager MUST:
Options
- AUpdate the risk register.
- BImplement the change.
- CCancel the project.
- DGenerate a change request.
How the community answered
(47 responses)- A4% (2)
- B13% (6)
- C2% (1)
- D81% (38)
Community Discussion
No community discussion yet for this question.