Question

After a project team has almost completed the development on the project's original requirements, the users identify functionality that is necessary but was not in the original requirements. The project manager MUST:

Options

  • AUpdate the risk register.
  • BImplement the change.
  • CCancel the project.
  • DGenerate a change request.