JK0-017 · Question #173

A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The…

The correct answer is D. Scope creep. See the full explanation below for the reasoning.

Question

A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The project manager implements the functionality while waiting for approval. This is known as which of the following?

Options

  • AChange request
  • BRisk
  • CResource constraint
  • DScope creep

How the community answered

(46 responses)
  • A
    20% (9)
  • B
    7% (3)
  • C
    4% (2)
  • D
    70% (32)