JK0-017 · Question #17

A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the…

The correct answer is B. Planned value. See the full explanation below for the reasoning.

Question

A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?

Options

  • AEstimate to completion
  • BPlanned value
  • CCost performance index
  • DBudget at completion

How the community answered

(27 responses)
  • A
    11% (3)
  • B
    70% (19)
  • C
    15% (4)
  • D
    4% (1)