A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the…
The correct answer is B. Planned value. See the full explanation below for the reasoning.
Question
A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,000. Which of the following will the project manager use to determine the budgeted cost of work scheduled?
Options
- AEstimate to completion
- BPlanned value
- CCost performance index
- DBudget at completion
How the community answered
(27 responses)- A11% (3)
- B70% (19)
- C15% (4)
- D4% (1)