nerdexam
CompTIA

JK0-017 · Question #16

JK0-017 Question #16: Real Exam Question with Answer & Explanation

Sign in or unlock JK0-017 to reveal the answer and full explanation for question #16. The question stem and answer options stay visible for context.

Question

A project was originally budgeted for $500,000. So far, the EV and AC on the project are equal. Two approved change requests have been submitted since the project began. One necessitated a change in the project that would increase costs by $50,000. The second change request increased costs by $270,000. Which of the following is the new BAC for the project?

Options

  • A$500,000
  • B$550,000
  • C$820,000
  • D$920,000

Unlock JK0-017 to see the answer

You've previewed enough free JK0-017 questions. Unlock JK0-017 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full JK0-017 Practice