nerdexam
CompTIA

JK0-017 · Question #16

A project was originally budgeted for $500,000. So far, the EV and AC on the project are equal. Two approved change requests have been submitted since the project began. One necessitated a change in…

The correct answer is C. $820,000. See the full explanation below for the reasoning.

Question

A project was originally budgeted for $500,000. So far, the EV and AC on the project are equal. Two approved change requests have been submitted since the project began. One necessitated a change in the project that would increase costs by $50,000. The second change request increased costs by $270,000. Which of the following is the new BAC for the project?

Options

  • A$500,000
  • B$550,000
  • C$820,000
  • D$920,000

How the community answered

(31 responses)
  • A
    10% (3)
  • B
    3% (1)
  • C
    84% (26)
  • D
    3% (1)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice