JK0-017 · Question #16
A project was originally budgeted for $500,000. So far, the EV and AC on the project are equal. Two approved change requests have been submitted since the project began. One necessitated a change in…
The correct answer is C. $820,000. See the full explanation below for the reasoning.
Question
A project was originally budgeted for $500,000. So far, the EV and AC on the project are equal. Two approved change requests have been submitted since the project began. One necessitated a change in the project that would increase costs by $50,000. The second change request increased costs by $270,000. Which of the following is the new BAC for the project?
Options
- A$500,000
- B$550,000
- C$820,000
- D$920,000
How the community answered
(31 responses)- A10% (3)
- B3% (1)
- C84% (26)
- D3% (1)