A project has two resources scheduled to work 40 hours a week for four weeks, both at $85.00 an hour. One resource called in sick for 16 hours, while the other resource worked four hours additional…

The correct answer is B. $26,180. See the full explanation below for the reasoning.

Question

A project has two resources scheduled to work 40 hours a week for four weeks, both at $85.00 an hour. One resource called in sick for 16 hours, while the other resource worked four hours additional. Which of the following is the cost of the resources?

Options

  • A$25,840
  • B$26,180
  • C$27,200
  • D$27,540

How the community answered