A project has been going on for three weeks, and the project manager notices that Resource A is beginning to fall behind schedule. The project manager should FIRST schedule a meeting with:
The correct answer is B. Resource A to confirm estimates. See the full explanation below for the reasoning.
Question
A project has been going on for three weeks, and the project manager notices that Resource A is beginning to fall behind schedule. The project manager should FIRST schedule a meeting with:
Options
- AThe project stakeholders to communicate the delay.
- BResource A to confirm estimates.
- CThe other team members to make up the schedule slippage.
- DThe manager of Resource A for corrective action.
How the community answered
(56 responses)- A14% (8)
- B73% (41)
- C4% (2)
- D9% (5)