JK0-017 · Question #158

If the SPI and CPI are both above 1, then the project is:

The correct answer is D. Ahead of schedule and under budget. See the full explanation below for the reasoning.

Question

If the SPI and CPI are both above 1, then the project is:

Options

  • ABehind schedule and under budget.
  • BBehind schedule and over budget.
  • CAhead of schedule and over budget.
  • DAhead of schedule and under budget.

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    4% (1)
  • C
    13% (3)
  • D
    75% (18)