Which of the following BEST describes a project risk?
The correct answer is A. Something that may positively or negatively impact the project. See the full explanation below for the reasoning.
Question
Which of the following BEST describes a project risk?
Options
- ASomething that may positively or negatively impact the project
- BSomething that has already affected the project
- CSomething that is outside of the control of the project manager
- DSomething that will negatively impact the project
How the community answered
(27 responses)- A85% (23)
- B4% (1)
- C4% (1)
- D7% (2)