Which of the following plans would MOST likely contain a probability and impact matrix?
The correct answer is C. Risk. See the full explanation below for the reasoning.
Question
Which of the following plans would MOST likely contain a probability and impact matrix?
Options
- ACommunication
- BResource
- CRisk
- DProject
How the community answered
(56 responses)- A11% (6)
- B4% (2)
- C79% (44)
- D7% (4)