Which of the following does the Critical Path tell the Project Manager? (Select TWO).
Options
- AWhere potential delays in the project might occur
- BThe earliest completion for project work
- CActivities that can be done in parallel
- DThe allocation time for each person assigned to the project
- EThe longest series of activities