Which of the following does the Critical Path tell the Project Manager? (Select TWO).
The correct answer is B. The earliest completion for project work E. The longest series of activities. See the full explanation below for the reasoning.
Question
Which of the following does the Critical Path tell the Project Manager? (Select TWO).
Options
- AWhere potential delays in the project might occur
- BThe earliest completion for project work
- CActivities that can be done in parallel
- DThe allocation time for each person assigned to the project
- EThe longest series of activities
How the community answered
(34 responses)- A9% (3)
- B71% (24)
- C18% (6)
- D3% (1)