A project manager learns that a key staff member is making unauthorized product changes. How will this impact the project?

The correct answer is B. Scope creep will occur. See the full explanation below for the reasoning.

Question

A project manager learns that a key staff member is making unauthorized product changes. How will this impact the project?

Options

  • AQuality standards will improve
  • BScope creep will occur
  • CRisks will decrease
  • DAcceptance testing will decrease

How the community answered

(39 responses)
  • A
    10% (4)
  • B
    82% (32)
  • C
    3% (1)
  • D
    5% (2)