Through which process does the implementation of a new or changed service, including closure of a service, need to be planned and approved?
The correct answer is B. Change management. You've hit your weekly limit · resets 5am (America/New_York)
Implementation and transition of new or changed services
Question
Through which process does the implementation of a new or changed service, including closure of a service, need to be planned and approved?
Options
- ABusiness relationship management
- BChange management
- CRelease management
- DService level management
How the community answered
(22 responses)- A9% (2)
- B82% (18)
- C5% (1)
- D5% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#change management#service implementation#approval#new services