ITSM20F.EN · Question #70

Through which process does the implementation of a new or changed service, including closure of a service, need to be planned and approved?

The correct answer is B. Change management. You've hit your weekly limit · resets 5am (America/New_York)

Implementation and transition of new or changed services

Question

Through which process does the implementation of a new or changed service, including closure of a service, need to be planned and approved?

Options

  • ABusiness relationship management
  • BChange management
  • CRelease management
  • DService level management

How the community answered

(22 responses)
  • A
    9% (2)
  • B
    82% (18)
  • C
    5% (1)
  • D
    5% (1)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#change management#service implementation#approval#new services