ITSM20F.EN · Question #110
One of the activities of Release and deployment management involves testing and Release acceptance. When can Release management start with implementation planning?
The correct answer is C. As soon as Change management has approved the Release. You've hit your weekly limit · resets 5am (America/New_York)
Implementation and transition of new or changed services
Question
One of the activities of Release and deployment management involves testing and Release acceptance. When can Release management start with implementation planning?
Options
- AAs soon as the documentation for managing and supporting the Release is also complete and up
- BAs soon as the users have tested the Release.
- CAs soon as Change management has approved the Release.
- DAs soon as the technicians have tested the Release and no adverse impact of this Release is
How the community answered
(37 responses)- A3% (1)
- B8% (3)
- C76% (28)
- D14% (5)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#release management#change management approval#implementation planning#release acceptance