The success and failure of Releases shall be measured. What is included in these measurements?
The correct answer is B. The Incidents related to a Release in the period following a Release. You've hit your weekly limit · resets 5am (America/New_York)
Implementation and transition of new or changed services
Question
The success and failure of Releases shall be measured. What is included in these measurements?
Options
- AThe frequency and types of Releases
- BThe Incidents related to a Release in the period following a Release
- CThe Release dates
- DThe Request for Change (RFC)
How the community answered
(29 responses)- A14% (4)
- B76% (22)
- C7% (2)
- D3% (1)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#Release Management#measurement#post-release incidents#metrics